The connection permit (ATR)

The document issued by the network operator that sets the technical connection conditions, the delimitation point and the deadlines — and that opens the connection contract.

Direct answer
Issued by the network operatorStage 3 of 4ANRE Order no. 59/2013

The connection permit (ATR) is the document issued by the network operator that sets the technical conditions for connecting to the electricity grid. The ATR fixes the delimitation point between the client's installation and the operator's network, the contribution to network development and the deadlines, and underpins the connection contract.

What is a connection permit (ATR)?

The connection permit is the network operator's official technical answer to a connection request. It is not an approval in principle and it is not a commercial offer: it is the document that describes, in technical terms, exactly how a consumption or generation site can be connected to the public electricity network.

The ATR is issued on the basis of a connection solution established beforehand, through a solution sheet or a solution study. That is why the quality of the solution study largely determines the conditions that end up in the ATR — the connection point, the works required and the operating restrictions.

PowerGrid Solution does not issue connection permits. As an ANRE-attested designer, the company substantiates the solution through the solution study, supports the technical clarifications with the operator, and then uses the issued ATR as an input document for the technical design.

What does the connection permit set?

The ATR fixes the elements that the rest of the project treats as given. Four of them matter to any client.

  • The technical connection conditions: approved capacity, voltage level, equipment and protection requirements
  • The delimitation point between the client's installation and the network operator's network
  • The contribution to network development
  • The deadlines attached to the connection

When do you need an ATR?

A connection permit is required whenever a new link to the public electricity network is created, or an existing one is changed in its technical parameters.

  • A new consumption site: warehouse, industrial platform, building, public facility
  • An increase over the capacity previously approved for an existing site
  • A new generation site: photovoltaic park, power plant, cogeneration
  • An energy storage system connected to the grid, on its own or together with generation
  • Changes to the electrical installations upstream of the delimitation point

Which documents lead to the issuing of an ATR?

An ATR is not requested directly: it is obtained at the end of the connection request. The file lodged with the network operator usually contains the client's identification data, the site plan, the urban planning certificate, the cadastral data, the requested capacity and the consumption or generation profile.

Where the solution is set through a solution study, the study — produced by an ANRE-attested designer and approved by the operator — is added to the file. The exact list of documents is confirmed by the network operator, because it differs with the type of consumption or generation site and with the voltage level.

Who issues the ATR and who substantiates it?

The connection permit is issued exclusively by the network operator covering the site. A designer can neither issue it nor promise it; the designer's role is to build the technical solution that the operator then approves.

That separation is why a serious designer does not guarantee a particular permitting outcome. What can be guaranteed is the quality and completeness of the documentation presented to the operator, plus support through the technical clarifications raised during the review.

How long is an ATR valid and what happens when it expires?

The connection permit has a validity period, and the connection contract is signed within it. The request to sign the connection contract is filed a set period ahead of the ATR's expiry date, as established by the regulation.

PowerGrid Solution does not publish that number of days here, because the deadlines differ between the variants of the process and change with the regulation. The official ANRE documents linked below carry the deadline for each step, including the one for requesting the connection contract.

The practical consequence for an investor is simple: an ATR obtained and left unused loses its purpose, and restarting means a new file. A project schedule is built starting from the ATR's validity, not the other way round.

What follows the issuing of the ATR?

After the ATR, the connection contract is signed with the network operator. Then come the reinforcement works upstream of the connection point, where the solution called for them, followed by the design and construction of the connection installation.

At this stage the ATR becomes an input document for the technical design: technical report, electrical diagrams, sizing calculations, drawings, installation details and bills of quantities. At the end, after acceptance and commissioning, the operator issues the connection certificate.

How do the ATR, the solution study and the connection certificate differ?

The three documents are frequently confused, although they belong to different moments of the process and have different issuers.

  • The solution study is a technical document produced by an ANRE-attested designer, comparing the connection alternatives and substantiating the solution.
  • The connection permit is issued by the network operator on the basis of the chosen solution, and sets the technical conditions, the delimitation point, the contribution to network development and the deadlines.
  • The connection certificate is also issued by the network operator, but at the end of the process, after the installations have been accepted and commissioned.
Costs

Which costs appear around the connection permit

There is no single price for an ATR, because the financial obligations around it are set by different parties. PowerGrid Solution neither charges nor sets any of them; they are listed here so it is clear who asks for what.

  • The contribution to network development, set through the ATR by the network operator
  • The cost of drawing up and approving the solution study, where the solution is set that way — per the notes of the ANRE document on the stages of the connection process
  • The connection installation works and any network reinforcement works called for by the solution
  • For producers above 1 MW, the issuing of the ATR is conditional on a financial guarantee constituted in favour of the network operator, per the same ANRE notes

The actual figures are communicated by the network operator, case by case. PowerGrid Solution quotes only the design work — solution study, impact study, technical design — once it has seen the site data and the requested capacity.

Official sources

Where the ATR rules can be checked

The ANRE documents below describe the step at which the connection permit is issued, the associated deadlines and the notes on the solution study and the financial guarantee. The specific conditions are confirmed with the network operator at the date of the request.

FAQ

Frequently asked questions about the connection permit

The connection permit is the document issued by the network operator setting the technical conditions under which a consumption or generation site may be connected to the public electricity network. It fixes the delimitation point, the contribution to network development and the connection deadlines.